  1. Land purchase is usually done 2 – 3 years prior
  2. Product design and features determined
  3. Development (streets and utilities) about a year prior
  4. Building permits are submitted and they tend to take about one to two months (per county)

(Please note that due to COVID-19 and supply chain issues timelines may take a lot longer right now)


After all the behind the scenes things happen, then the actual building of the home can begin….or as we call it, “The Fun Part”!

 Even after 7,000 homes, our team still finds it very exciting and interesting to watch a new home come to life.

This timeline is for a 2,000 – 3,000 square foot home which can take about 120 to 150 days to build.   

This timeline is BASED ON a 130 day build cycle for example purposes.

Day 130

Day 1

Job Initiation Order (JIO) sent to superintendent
Days 2– 25

Days 2– 25

Order Framing Package • Order roof truss system • Footing/slab material • Temporary Electric • Footing install Block material & pin footing • Block labor • Foundation survey & setbacks verified • Utility install • Plumbing in slab and safety grade • Plumbing inspection • Slab prep 1 inspection
Days 25 – 40

Days 25 – 40

Slab Pour • Slab Pour Inspection • Rough framing • Order windows/doors exterior • Measure for cabinets • Housewrap installed
Days 41 – 45

Days 41 – 45

Framing continues • Roof material drop off • Sheathing Housewrap inspection • Roofing labor • Dumpster drop off/pick up #1 • Schedule gas line (if needed) • Windows/doors install exterior • Confirm and order cabinets final • Framing punch out #1
Days 46 – 50

Days 46 – 50

Plumbing rough in • Fireplace rough in • Measure for interior doors • Finish roofing • HVAC rough in • Install roofing pipe boots • Order brick/stone/siding delivery • Quality Control punch out list due
Days 51 – 58

Days 51 – 58

Electrical rough in • Brick/stone material drop off • Media/security system rough • Fireplace inspection • Brick/stone labor • Low voltage inspection • HVAC rough in inspection • Framing punch out #2 • Plumbing rough inspection • Electrical rough inspection
Days 59 – 65

Days 59 – 65

Quality Control Insulation inspection • Inspections for all custom features pre-drywall • Order drywall • Order siding
Days 66 – 72

Days 66 – 72

Drywall material drop off • Drywall install • Roofing shingles install • Order exterior paint • Siding install • Gas line install • Electrical meter base install • Exterior paint • Trim material ordered • Gutters • Rough grade
Days 73 – 90

Days 73 – 90

Trim labor • Fireplace mantle trim out • Dumpster #2 • Concrete flatwork (driveway) • Deck install • Paint interior #1 • Irrigation sleeves • Electric meter • Tile shower • Cabinet delivery • Cabinet install • Lighting delivery • Shower door measure • Ceiling insulation blow in • Drywall point up • Set columns
Days 91 – 94

Days 91 – 94

Electrical trim out #1 • Measure for granite • Install vinyl • Install LVP/EVP and tile • Install hardwoods • Water heater delivery • Shoemold install and stain/paint • HVAC trim out • Drywall point and sand
Days 95 – 98

Days 95 – 98

Interior paint #2 • Granite and sinks install • Appliances order • Garage door install • Gas meter inspection • Shutter in stall (if have any) • Tile backsplash install • Plumbing trim out (hook up water heater, hook up sinks) • Final grading • Gas meter install • Electrical trim out #2 (lighting installed) • Final plumbing inspection • Meda/alarm trim out
Days 99 – 101

Days 99 – 101

Trim accessories and shower door install • HVAC start up • Final electrical inspection • Final mechanical inspection • Landscaping • Railings install • Carpet • Cabinet shoe mold and touch up • Sod install • First cleaning • Dumpster #3
Days 102 – 105

Days 102 – 105

Pressure wash exterior • Termite install • House numbers installed • Window screens (per community) • Final inspection
Days 106 – 119

Days 106 – 119

Touch up clean #1 • Quality control • Quality control trim labor • Quality control drywall touch up • Quality control paint touch up
Days 120 – 129

Days 120 – 129

Appliances install • First walk through • Punch out done • Touch up clean #2 • Final walk through
Day 130

Day 130

Close * Get Your Keys! * Move In
After The Closing

After The Closing

Register Your New Home’s Warranty • See What’s Next on our Website’s Homeowner Section

Please remember, this can and probably will very as needed to meet each home buyer’s and home’s unique circumstances.  


FYI, we plan on a certain amount of possible delays in our timeline, so while we add in extra time, we still cannot predict them all.  

Here are some of the more usually causes of delays:

  1. Larger homes with lots of custom features
  2. Basements usually add 2 months to the build cycle
  3. Sudden changes to government regulations
  4. Supply chain issues – if we can’t get it, we can’t install it, and if we can’t install it, that may also prevent us from going to the next step 
  5. Weather delays – in Georgia, winter freezes and spring rains can cause some longer than unexpected delays
  6. Sudden changes to subcontractors

    Our team takes this very seriously and wants to make each closing happen on time.  Each of us understands how challenging a move can be from the home buyers perspective, because all of our members has been there.  We get it!!

Home-Buying-15

We are here to help, so if you have any questions, please ask the onsite agent that is working with you.


Are You Ready to See What MORE Chafin Can Do For YOU?

Buying a home is an exciting time and choosing the perfect home for your lifestyle or family is a huge decision.  Let our ONLINE Specialists guide you! 

 Contact Us Today: ONLINE Chat or Call 1-470-269-3829.

VIEW THE CHAFIN HOME BUYING PROCESS